Part 3
The North stand is now fully roofed, brickwork is however still in the preliminary stages. Cladding has also gone on to form the back wall of the stand
The storm water attenuation tank behind the North stand is mostly filled in now, and as a result you get a good idea of the size of the north stand car park.
In the background wood fencing can be seen separating the Tescos from the stadium site
Moving onto the west home terrace.
Brickwork on this stand looks about 10 feet high, as its above the height of the transit van
Note also the tractor which has a trailer to lay seed for the pitch
Close to Peasley cross road they are also concreting the top of the stone gabbions
More shots of the stadium
I think it will look very impressive for people traveling into the Tescos car park